[edit] Definition
The document "Building Blocks; a manifesto to transform the Built Environment" published by Architects Declare defines a pre-demolition audit as
"a survey carried out by qualified personnel to determine the quantity of material in a building before its demolition or deconstruction. It helps to identify materials within the building that could be reused or repurposed."
[edit] Introduction
It’s always best, when considering demolishing a building, to ask certain questions before beginning any work – even planning work. The first, and perhaps the biggest, is to ask why you want to demolish the existing site – can it be redeveloped or can elements of the site be kept?
A pre-demolition audit can help answer these questions, along with assessing the materials within the buildings and their potential value. When you have all of this information, that’s when you need to look at whether to refurbish, renovate or demolish.
[edit] So, you have decided to demolish
What will you be doing with all of those materials? Best practice says you should try to reclaim as much waste as possible, and there are four key ways to handle demolition waste reclamation, known as the Four R’s – each with their own advantages:
[edit] Reduce
Are there any areas of the building you can keep? Reducing the amount of waste through not demolishing a part of a building will help you to save time and money through sorting or transportation.
[edit] Reuse
What areas can be reused in their current form? Timber or metal beams, intact fireplaces, heating or electrical systems? If these, and more, can be reused in the new building on the same site, this will help you save on some new build materials cost and will reduce time spent recycling or disposing of materials, saving time in the process.
[edit] Recycle
When materials on your site can’t be reused, can they be recycled? This is taking the materials and using them in a different form, for example taking a timber beam and shredding this, to reform into MDF or a similar material – for use in the new building.
[edit] Recover
This option is often best for teams that aren’t able to go through options 1-3, for example if there’s little time to complete these activities. Recovering materials in essence a means to send all mixed (unsorted) waste materials to a facility, where they will look to reuse or recycle them externally.
The more material that can be dealt with using a mixture of the above options, the greater the chance of saving money through on build costs, selling materials that have been identified as having value, or even just avoiding landfill tax.
This article was created by --BRE Buzz. It was originally published on BRE Buzz in March 2016 and was written by Jo Goodwin, Marketing Manager for BRE SMARTWaste and BRE YellowJacket.
You can see the original article here.
Read more BRE Buzz articles here.
[edit] Related articles on Designing Buildings
- Building Research Establishment.
- BRE articles.
- BRE Trust.
- BREEAM.
- Decommissioning.
- Demolition.
- Design for deconstruction – helping construction unlock the benefits of the circular economy.
- End of life potential.
- Explosives.
- How to conduct a pre-demolition audit.
- Pre-construction information.
- Quantification of construction materials in existing buildings (material intensity).
- Recycling.
- Site waste management plan.
- Sustainable materials.
Featured articles and news
Shortage of high-quality data threatening the AI boom
And other fundamental issues highlighted by the Open Data Institute.
Data centres top the list of growth opportunities
In robust, yet heterogenous world BACS market.
Increased funding for BSR announced
Within plans for next generation of new towns.
New Towns Taskforce interim policy statement
With initial reactions to the 6 month policy update.
Heritage, industry and slavery
Interpretation must tell the story accurately.
PM announces Building safety and fire move to MHCLG
Following recommendations of the Grenfell Inquiry report.
Conserving the ruins of a great Elizabethan country house.
BSRIA European air conditioning market update 2024
Highs, lows and discrepancy rates in the annual demand.
50 years celebrating the ECA Apprenticeship Awards
As SMEs say the 10 years of the Apprenticeship Levy has failed them.
Nominations sought for CIOB awards
Celebrating construction excellence in Ireland and Northern Ireland.
EPC consultation in context: NCM, SAP, SBEM and HEM
One week to respond to the consultation on reforms to the Energy Performance of Buildings framework.
CIAT Celebrates 60 years of Architectural Technology
Find out more #CIAT60 social media takeover.
The BPF urges Chancellor for additional BSR resources
To remove barriers and bottlenecks which delay projects.
Flexibility over requirements to boost apprentice numbers
English, maths and minimumun duration requirements reduced for a 10,000 gain.
A long term view on European heating markets
BSRIA HVAC 2032 Study.
Humidity resilience strategies for home design
Frequency of extreme humidity events is increasing.
National Apprenticeship Week 2025
Skills for life : 10-16 February